Great River Energy Spill Prevention, Control, and Countermeasures Plans for Electrical Substations Throughout Minnesota

Great River Energy Spill Prevention, Control, and Countermeasures Plans for Electrical Substations Throughout Minnesota

Great River Energy Spill Prevention, Control, and Countermeasures Plans for Electrical Substations Throughout Minnesota

Background

The Clean Water Act and 40 CFR 112, as amended, require certain non-transportation-related oil storage and consumption facilities to maintain a Spill Prevention, Control, and Countermeasures (SPCC) Plan. Electrical substations contain oil-filled equipment and are therefore subject to these regulations.

The criteria used to evaluate whether an SPCC Plan is required for an electrical substation include the following:

  • Aboveground storage facility that contains more than 1,320 gallons of oil (total). Single pieces of equipment containing 55 gallons or less do not count towards the total volume of oil.
  • An electrical substation that, due to its location and aforementioned oil-containing equipment capacities, could reasonably be expected to discharge oil to the waters of the United States, adjoining shorelines, or protected resources in the event of a spill.

A spill event includes a discharge of oil into or upon navigable waters, adjoining shorelines, or protected resources in a quantity sufficient to cause an oil slick or sheen on the surface of the water. Navigable waters is defined in 40 CFR Part 112, Section 112.2, and includes all waters with a past, present, or possible future use in interstate or foreign commerce, including all waters subject to the ebb and flow of the tide; all interstate waters including interstate wetlands; and all other waters such as intrastate lakes, rivers, streams, mudflats, sandflats, wetlands, sloughs, prairie potholes, wet meadows, playa lakes, or natural ponds, whose use, degradation, or destruction could affect interstate or foreign commerce.

The Project

HEI worked cooperatively with Great River Energy (GRE), Crow Wing Power, Lake Country Power, Mille Lacs Electric Cooperative, Arrowhead Electric Cooperative, Inc., North Itasca Electric Cooperative, Cooperative Light and Power, Head of the Lakes Cooperative, and Agralite Electric Cooperative to evaluate and prepare SPCC Plans as appropriate.

HEI’s approach to the SPCC Plans was to work jointly with GRE and its member cooperatives to gather background information for the respective substations. This was followed by a field evaluation whereby the site and adjacent areas were investigated and any nearby navigable waters identified. HEI analyzed the background and field data and performed spill modeling, if applicable, using the Mineral Oil Spill Evaluation System (MOSES), which was developed by the Electric Power Research Institute. Following this analysis, the team prepared an Evaluation, Analysis, or SPCC Plan for the electric substation.

The ultimate purpose of the SPCC Plan is to help prevent spill events and, in the event of a spill, to outline the proper procedures to control such events.

  • Performed the required fieldwork and obtained information for each substation site in order to perform the MOSES analysis.
  • Represented GRE and worked cooperatively with GRE’s member cooperatives in preparing the SPCC Plans.
  • Developed an approach for evaluating the substation sites and categorizing them in terms of their plan requirements; either a spill plan, an analysis, or an evaluation.
  • Worked jointly with GRE and its member cooperatives to develop spill plans, analyses, and evaluations for the substation sites that satisfied the requirements of the Clean Water Act and 40 CFR 112, and the requirements specific to each member cooperative.
Project Details

Location: Substation Sites located Throughout Minnesota

Project Highlights
  • Performed the required fieldwork and obtained information for each substation site in order to perform the MOSES analysis.
  • Represented GRE and worked cooperatively with GRE’s member cooperatives in preparing the SPCC Plans.
  • Developed an approach for evaluating the substation sites and categorizing them in terms of their plan requirements; either a spill plan, an analysis, or an evaluation.
  • Worked jointly with GRE and its member cooperatives to develop spill plans, analyses, and evaluations for the substation sites that satisfied the requirements of the Clean Water Act and 40 CFR 112, and the requirements specific to each member cooperative.
Services

Ready to start a project?

Get in touch with our Environmental experts today.

Related Projects

Clean Fuels Alliance America−GREET Emissions Calculator
View More
Great River Energy Route Analysis for a Project Corridor Between Athens and Martin Lake Substations
View More
Otter Tail Power Company Spill Prevention, Control, and Countermeasure Plans
View More
Cass County Highways 23 and 10, Casselton Ethanol Plant Two Mile Reconstruct–10-Inch PCC Pavement
View More
Scroll to Top

Grant Research

We begin by thoroughly researching available grant opportunities to identify those best suited to your specific project needs. Our team leverages our deep understanding of federal, state, and local grant programs, as well as foundation grants, to ensure a comprehensive search. We evaluate eligibility criteria, funding priorities, and timelines to match your project with the most appropriate funding sources. This targeted approach maximizes the potential for securing financial support for your project.